A China Council for the Promotion of International Trade (Kínai Népköztársaság Kereskedelemfejlesztési Hivatala) Changchun-i Hivatala által közzétett listát képező projektekhez a kínai fél üzleti partnereket keres.

 

Key Economic Cooperative Projects ofChangchunCityin 2012

ChangchunMunicipal Bureau of Commerce 

January 2012

 

I. Projects for Production of Automobile and Auto Spare Parts (19)

 

1  Project with annual production of 30,000 agricultural vehicles

1. Total investment in the project: 640 million yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers a total of160,000 m2land, with floor area of112,000 m2.

5. Anticipated economic benefits: After achieving designed capacity, the annual output value will be 1.8 billion yuan, with annual profit of 180 million yuan, tax payment of 540 million yuan, and investment recovery period of 6.3 years.

6. Contact: Xie Hong

7. Tel: 0086-431-87806877

 

2  Project with annual production of painting, stamping, and welding of 200,000 sets of whole vehicles

1. Total investment in the project: 850 million yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project occupies a total area of210,000 m2land, with floor area of150,000 m2, including120,000 m2for factory buildings, and30,000 m2for office buildings.

5. Anticipated economic benefits: After reaching the designed capacity, the annual output value will be 2 billion yuan, with annual profit of 200 million yuan, tax payment of 60 million yuan, and investment recovery period of 8 years.

6. Contact: Xie Hong

7. Tel: 0086-431-87806877

 

3  Project with annual production of 100,000 sets of automotive leather seats

1. Total investment in the project: 50 million yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Annual production of 100,000 sets of automotive leather seats.

5. Anticipated economic benefits: Annual sales income will reach 120 million yuan, with net profit of up to 27.616 million yuan, and investment recovery period of 3 years (including construction period).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

4  Project with annual production of 10 million automotive lithium batteries

1. Total investment in the project: 900 million yuan

2. Location of the construction site: Special-Purpose Vehicle Industrial Park of Changchun Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Construct production base with annual production of 10 million automotive lithium batteries. Planned occupation of land is100,000 m2, with floor area of60,000 m2mainly to build factories and office buildings.

5. Anticipated economic benefits: Annual output value will reach 3.5 billion yuan, with profits of 590 million yuan, and investment recovery period of 3.2 years.

6. Contact: Zhou Yiwen

7. Tel: 0086-431-84809076, 13604361994, 13353102767

 

5  Project with annual production of 3 million sets of automotive wheel hubs

1. Total investment in the project: 300 million yuan

2 Location of the construction site: Special-Purpose Vehicle Industrial Park of Changchun Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Planned occupation of land is40,000 m2with floor area of20,000 m2, mainly for construction of plant, technical center and trial workshop, and office buildings. Scale of construction: annual production of 3 million automotive wheel hubs.

5. Anticipated economic benefits: After completion of the project, the annual production will be 3 million sets of automotive wheel hubs, with expected output value of 1.5 billion yuan, tax payment of 150 million yuan, and investment recovery period of 4 years (including construction period).

6. Contact: Zhou Yiwen

7. Tel: 0086-431-84809076, 13604361994, 13353102767

 

6  Project with annual production of 100,000 units of on-vehicle GPS navigation and positioning systems

1. Total investment in the project: 900 million yuan

2. Location of the construction site: Automotive electronics Industrial Base,PhotoelectricInformationIndustrial Park, Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Planned land occupation of the project is60,000 m2, with floor area of90,000 m2, mainly for construction of production plant, office building, research center and other ancillary facilities.

5. Anticipated economic benefits: After completion of the project, the production scale will reach up to annual production of 100,000 units of automotive GPS navigation and positioning systems, with estimated annual revenue of 250 million yuan, total annual profit of 100 million yuan, and investment recovery period of 8 to 10 years.

6. Contacts: Liu Junfeng, Li Hanning

7. Tel: 0086-431-85828798

 

7  Project with annual production of machining of 400,000 sets of active and passive bevel gears of automotive driving axles

1. Total investment in the project: 120 million yuan

2. Location of the construction site: Changchun Jiutai Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Establish production capacity of annually 400,000 sets of basin angle gears; build office building, workshop No.1, and workshop No.2, with gross floor area of23,000 m2.

5. Anticipated economic benefits: After completion of the project and achievement of the designed capacity, the annual revenue will be 106.04 million yuan, with after-tax annual profit of 16 million yuan, and investment recovery period of: before tax: 5 years (including construction period); after tax: 5.25 years (including construction period of 5 years)

6. Contact: Manager Zhang

7. Tel: 18043122219

 

8  Project with annual production of 100,000 sets of automotive machine tools, hydraulic systems and other auto parts

1. Total investment in the project: 300 million yuan

2. Location of the construction site: North Sector of Changchun Jiutai Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Construct production facilities for annual production of 100,000 units (sets) of automotive machine tools, sheet metal, engines, hydraulic systems, bearings, seats and other auto parts, and new workshop, office, etc.

5. Anticipated economic benefits: Sales income of 420 million yuan, profit of 55 million yuan.

6. Contact: Zhang Yuhua

7. Tel: 0086-431-82563334

 

9  Project with annual production of 150,000 sets of car clutch, brake assembly, and other auto parts

1. Total investment in the project: 300 million yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project occupies a total area of93,000 m2, with floor area of64,000 m2, including52,000 m2for factory buildings, and12000 m2for office buildings.

5. Anticipated economic benefits: After reaching the designed capacity, the annual output value will be 500 million yuan, with annual profit of 75 million yuan, and investment recovery period of 6.3 years.

6. Contact: Xie Hong

7. Tel: 0086-0431-87806877

 

10  Project with annual production capacity of 1.8 million sets of automotive wiring harness

1.Total investment in the project: 300 million yuan

2.Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project occupies a total area of93,000 m2, with floor area of65,000 m2, including50,000 m2for three factory buildings, and15,000 m2for one office building.

5.Anticipated economic benefits: After reaching the designed capacity, the annual output value will be 500 million yuan, with annual profit of 120 million yuan, and investment recovery period of 7 years.

6.Contact: Xie Hong

7.Tel: 0086-431-87806877

 

11  Project with annual production capacity of 500,000 sets of automotive lamps

1. Total investment in the project: 200 million yuan

2. Location of the construction site: Longwang village, Nong’an county,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers a total area of100,000 m2, with floor area of60,000 m2, planned annual production of 500,000 sets of automotive lamps.

5. Anticipated economic benefits: After the completion of the project, the annual sales income will be 500 million yuan, with profit of 26.4 million yuan, tax payment of 3.6 million yuan.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

12  Project with annual production of 200,000 sets of automotive steering boosters

1. Total investment in the project: 500 million yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Production program for annual production of 100,000 sets of steering boosters for commercial vehicles as well as 100,000 sets of steering boosters for passenger cars.

5. Anticipated economic benefits: Annual revenue is estimated to reach up to 600 million yuan, with profit of 130 million yuan, and annual tax payment of 56 million yuan.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

13  Project with annual production of 1.25 million automotive fuel tanks

1. Total investment in the project: 140 million yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project plans to construct the production capacity for an annual production of 1.25 million automotive plastic fuel tanks.

5. Anticipated economic benefits: A total profit of 161.96 million yuan will be realized, with static investment recovery period of 4.46 years and dynamic investment recovery period of 5.57 years.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

14  Project with annual production of 4 million sets of automotive wheel hubs

1. Total investment in the project: 140 million yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Mainly to construct standard industrial plant and office building, etc. The main product is automotive wheel hubs, with annual production of 4 million units.

5. Anticipated economic benefits: Annual revenue is estimated to reach up to 200 million yuan, with profit of 70 million yuan, and annual tax payment of 36 million yuan.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

15  Project with annual production of 100,000 sets of automotive interiors

1. Total investment in the project: 300 million yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The floor area is40,000 m2. According to the production program, working on double shifts, the annual production will be 100,000 sets of car seats, inner door panels, car carpets, and inner panels for baggage compartment, and other interior parts.

5. Anticipated economic benefits: Annual revenue is estimated to reach up to 400 million yuan, with profit of 130 million yuan, and annual tax payment of 50 million yuan.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

16  Special-purpose vehicle production project

1. Total investment in the project: 100 million yuan

2. Location of the construction site:ShelingIndustrial Parkin Shuangyang district

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale:

Scientific and technical personnel of our company have successfully developed the first rain water (sewage) drains cleaning vehicle in the country. This vehicle will be able to completely release the municipal workers from heavy physical labor, and greatly improve the efficiency of their work. The vehicle runs automatically, and moves the wastes which are cleared out directly into the car without dropping onto the ground to avoid secondary pollution. Production scale: (1) multi-function snowplow: annual production of 200-300 units. (2) Rain water / sewage drains cleaning vehicles: annual production of 1,000-2,000 units.

5. Anticipated economic benefits:

After reaching designed capacity, the annual output value will be 200-300 million yuan, with profit of 50 million yuan, profit & tax 35 million yuan.

6. Contact: Wang Haiwei

7. Tel: 0086-0431-86112656, 13844886959

 

17  Automotive engine production project

1. Total investment in the project: 586 million yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: planned occupation of land is150,000 m2, with floor area of120,000 m2mainly for factory buildings and office buildings.

5. Anticipated economic benefits: After the completion of the project and achievement of the designed capacity, the annual output value is expected to be 500 million yuan, with profit of 190 million yuan and investment recovery period of 3.2 years.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

18  Automotive castings and parts manufacturing project

1. Total investment in the project: 204 million yuan

2. Location of the construction site: Changchun Chaoyang Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Annual production of 100,000 tons of automotive castings and 1.3 million sets of components and parts.

5. Anticipated economic benefits: After the completion of the project and achievement of the designed capacity the sales revenue is expected to grow by 550 million yuan, with gross profit of 56 million yuan.

6. Contacts: Zhang Bo, Zhai Yunfei, Ding Lin

7. Tel: 0086-431-85109189, 85109113

 

19  Project for production of polyester and polyurethane fire-retardant foam and textile fabric facing material used on limousine seats

1. Total investment in the project: 300 million yuan (including 210 million yuan financing)

2. Location of the construction site: Northeast Core Area of Changchun High-Tech Industrial Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Planned land occupation of the project is100,000 m2, with floor area of80,000 m2, mainly for construction of plants, warehouses and office buildings. Procurement of related equipment is also included in this project.

5. Anticipated economic benefits: After achievement of the designed capacity the annual sales revenue is expected to reach up to 400 million yuan, with profit of 80 million yuan.

6. Contact: Zhang Fusheng

7. Tel: 0086-431-85542551, 15843071966

 

 

II. Projects for Production of Railway Passenger Cars and Parts (16)

 

1  Project with annual production of 50 narrow-gauge MU trains

1. Total investment in the project: 649.17 million yuan

2. Location of the construction site: Equipment Manufacturing Park of Changchun Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Land occupation of Phase I of the project is250,000 m2; the production scale will be annual production of 50 narrow-gauge MU trains.

5. Anticipated economic benefits: Annual sales income of 1 billion yuan, with investment recovery period of 7.28 years (tax included)

6. Contact: Yang Xudong

7. Tel: 0086-431-8463 2683

 

2  Project with annual production of 50,000 sets of components and parts for railway passenger cars

1. Total investment in the project: 300 million yuan

2. Location of the construction site:

Lanjia town, Kuancheng district,Changchuncity – From Road C-27 inthe north, to Road C-26 inthe south, and from Road D-46 inthe west, to Road D-47 inthe east

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale:

Occupied land area is97,200 m2, with floor area of60,000 m2; annual production will be 50,000 sets of railway passenger car seats.

5. Anticipated economic benefits:

After achieving designed capacity, annual output value is estimated to be 300 million yuan, with total annual profit of up to 30 million yuan, and tax payment of up to 15 million yuan.

6. Contacts: Fu Deyong, Sun Jianbo, Qu Zhongliang

7. Tel: 0086-431-89990273, 89990733

 

3  Project with annual production of 800,000 square meters of decoration materials for railway passenger cars

1. Total investment in the project: 300 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is5 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be800,000 m2of decoration materials for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 500 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

4  Project with annual production of 2 million sets of electronic accessories for railway passenger cars

1. Total investment in the project: 200 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is4 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 2 million sets of electronic accessories for high-speed railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 400 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

5  Project with annual production of 2million sets of air-conditioning accessories for railway passenger cars

1. Total investment in the project: 400 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is5 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 2 million pieces of air-conditioning accessories for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 450 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

6  Project with annual production of 1.5 million meters of interior fabric materials for railway passenger cars

1. Total investment in the project: 100 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 1.5 million meters of interior fabric materials for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 200 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

7  Project with annual production of 2 million square meters of thermal insulation materials for railway passenger cars

1. Total investment in the project: 150 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 2 million square meters of thermal insulation materials for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 200 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

8  Project with annual production of 400,000 tons of aluminum profiles for railway passenger cars

1. Total investment in the project: 700 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 400,000 tons of aluminum profiles for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 150 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

9  Project with annual production capacity of 600 tractive transformers for railway vehicle

1. Total investment in the project: 900 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 500 sets of traction converters and 100 sets of auxiliary converters.

5. Anticipated economic benefits: Estimated annual sales income of 250 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

10  Project with annual production capacity of 8000 aluminium alloy workpieces for railway-vehicle

1. Total investment in the project: 90 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is1 hectares, divided into 2 phases to be constructed in 2 years. The annual production capacity for railway vehicle aluminium alloy workpiece will be 8000.

5. Anticipated economic benefits: Estimated annual sales income of 150 million yuan.

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

11  Project with annual production capacity of 500,000 square meters dalle for railway vehicle coach

1. Total investment in the project: 80 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production capacity for railway vehicle coach dalle will be500,000 square meters

5. Anticipated economic benefits: Estimated annual sales income of 160 million yuan.

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

12  Project with annual production capacity of 10,000 braking system accessories for railway vehicle

1. Total investment in the project: 90 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is1 hectares, divided into 2 phases to be constructed in 2 years. The annual production capacity for railway vehicle braking system accessories will be 10,000.

5. Anticipated economic benefits: Estimated annual sales income of 120 million yuan.

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

13  Project with annual production capacity of 1000 sets of information system for railway vehicle

1. Total investment in the project: 80 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is1 hectares, divided into 2 phases to be constructed in 2 years. The annual production capacity for railway vehicle information system will be 1000.

5. Anticipated economic benefits: Estimated annual sales income of 120 million yuan

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

14  Project with annual production of 50,000 sets of doors and windows for railway passenger cars

1. Total investment in the project: 90 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is1.5 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 50,000 sets of doors and windows for railway passenger cars.

5. Anticipated economic benefits: Annual sales income of 120 million yuan.

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

15  Project with annual production of 5,000 sets of molds for railway passenger cars

1. Total investment in the project: 290 million yuan

2. Location of the construction site: Changchun Lvyuan Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Overall planning area is2 hectares, divided into 2 phases to be constructed in 2 years. The annual production will be 5,000 sets of molds for railway passenger cars.

5. Anticipated economic benefits: Estimated annual sales income of 300 million yuan.

6. Contacts: Ma Mingxing, Hou Zhixiang

7. Tel: 0086-431-87886789, 87873807, 13756549977

 

16  Intensified manufacturing project of passenger cars accessories

1. Total investment in the project: 201,173,600 yuan

2. Location of the construction site: North Sector of Changchun Jiutai Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Main product of the project is whole vehicle of 8-12m skeleton-type passenger car (6-8m passenger car will also be considered) and 6-12m car frame. Two types of cars will be produced: the city passenger car series, and the road passenger car series. The project will have an annual production of 500 units in Phase I, 1,500 units in Phase II, and 2,000 units in Phase III.

5. Anticipated economic benefits: The annual sales income will be 860 million yuan, with total profit of 42.9 million yuan, and investment recovery period of 4.95 years.

6. Contact: Manager Wang

7. Tel: 13341484448

 

 

III. Agricultural and Sideline Products Deep Processing Projects (24)

 

1  Green organic rough-rice refined and deep processing project with annual production of 200,000 tons

1. Total investment in the project: 506,835,000 yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Refined and deep processing of green organic rough-rice with annual production of 200,000 tons.

5. Anticipated economic benefits: Annual sales income will reach 2,312 million yuan with net profit of up to 267.622 million yuan and investment recovery period of 2.9 years (including construction period of 1 year).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

2  Project with an annual production of 200,000 tons of beer brewed with mineral water

1. Total investment in the project: 223.34 million yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Annually processing 200,000 tons of beer brewed with mineral water.

5. Anticipated economic benefits: Annual sales income will reach 599.9 million yuan with net profit of up to 55.26 million yuan and investment recovery period of 4.3 years (after tax, including construction period of 1 year).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

3  Project with annual production of 200,000 tons of high-nutrient bio-organic fertilizer

1. Total investment in the project: 110.83 million yuan

2. Location of the construction site: Dehui city,Jilinprovince

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Annual production of 200,000 tons of high-nutrient bio-organic fertilizer. The project covers an area of70,000 m2, with floor area of21,720 m2.

5. Anticipated economic benefits: Annual sales income will reach 172 million yuan with net profit of up to 30.834 million yuan and investment recovery period of 5.4 years (including construction period of 1 year).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

4  Project with annual production of 150,000 tons of malt oligosaccharide syrup

1. Total investment in the project: 1 billion yuan

2. Location of the construction site: Changchun Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of50,000 m2and will annually produce 150,000 tons of malt oligosaccharide.

5. Anticipated economic benefits: After reaching the designed capacity, the annual output value is expected to reach 600 million yuan, with profit of 200 million yuan.

6. Contact: Tian Jiming

7. Tel: 0086-431-89960821

 

5  Project with annual production of 100,000 tons of straw briquettes

1. Total investment in the project: 30 million yuan

2. Location of the construction site: Clean Industrial Park, Changchun Shuangyang Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of13,000 m2, with floor area of6,800 m2, and will annually produce 100,000 tons of straw briquettes.

5. Anticipated economic benefits: After it is put into production, the project will create output value of 30 million yuan during the production period, with total profit of 17.29 million yuan, and investment recovery period of 3 years.

6. Contact: Zhang Dong

7. Tel: 0086-431-84152268

 

6  Project with annual production of 100,000 tons of mineral water

1. Total investment in the project: 76.57 million yuan

2. Location of the construction site: Qijia town, Shuangyang district,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Mineral water production plant, warehouse of raw materials, warehouse of finished products, boiler room, and etc. The annual production capacity is 100,000 tons of mineral water.

5. Anticipated economic benefits: The annual sales income will be 157 million yuan, with sales tax and additional tax 5.84 million yuan, total profit of 30.88 million yuan, and investment recovery period of 4.18 years.

6. Contact:Cao Zhanshan

7. Tel: 0086-431-84232006

 

7  Fruit and vegetable products deep processing project with annual production of 75,000 tons

1. Total investment in the project: 711.25 million yuan

2. Location of the construction site: Changchun Wukeshu Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Annual production of 490,000 tons of green vegetables, 5,000 tons of dehydrated vegetables, 20,000 tons of green pickles, and 50,000 tons of fruit and vegetable juices.

5. Anticipated economic benefits: After reaching the designed capacity, the project will realize annual sales income of 799.55 million yuan, with profit of 152.55 million yuan, and tax payment of 76.05 million yuan.

6. Contact: Zhang Xinchun

7. Tel: 0086-431-83810101

 

8  Project with annual production of 300,000 tons of corn straw fodders

1. Total investment in the project: 138.41 million yuan

2. Location of the construction site: Changchun Wukeshu Economic Development Zone

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: Annually producing corn straw fodders 300,000 tons.

5. Anticipated economic benefits: After achievement of the designed capacity, the annual sales revenue is expected to reach up to 154.2 million yuan, with profit of 25.99 million yuan.

6. Contact: Zhang Xinchun

7. Tel: 0086-431-83810004

 

9  Project with annual production of 8,000 tons of corn protein peptides

1. Total investment in the project: 388.22 million yuan

2. Location of the construction site: Changchun Yushu Huancheng Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Annually producing 5,000 tons of corn protein peptides for feed use, 2,000 tons of corn protein peptides for food use, and 1,000 tons of protein peptides for pharmaceutical use.

5. Anticipated economic benefits: After reaching the designed capacity, the project will realize annual sales revenue of 775.6 million yuan, with profit of 55.5 million yuan, and tax payment of 65.83 million yuan.

6. Contact: Hu Changming

7. Tel: 0086-431-83619188

 

10  Project with annual production of 100,000 tons of the medium-to-high grade liquor

1. Total investment in the project: 720 million yuan

2. Location of the construction site: Changchun Yushu Huancheng Industrial Cluster

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: Annually producing 100,000 tons of medium-to-high grade liquor.

5. Anticipated economic benefits: After reaching the designed capacity, the project will realize annual sales revenue of 1.8 billion yuan, with profit of 320 million yuan, and tax payment of 580 million yuan.

6. Contact: Zhang Guoxin

7. Tel: 0086-431-83863000

 

11  Project with annual production of 1 million tons of organic feed

1. Total investment in the project: 1 billion yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of200,000 m2, with floor area of150,000 m2.

5. Anticipated economic benefits: After reaching the designed capacity, the project will create annual output value of 800 million yuan, with annual profit of 200 million yuan, tax revenue of 100 million yuan, and investment recovery period of 7 years.

6. Contact: Xie Hong

7. Tel: 0086-431-87806877

 

12  Pepper deep processing project with annual production of 1,700 tons

1. Total investment in the project: 48 million yuan

2. Location of the construction site: Nong’an Industrial Cluster, in Nong’an county,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of20,000 m2, with floor area of10,000 m2, and will realize annual production capacity of 1,700 tons of pepper deep-processing products.

5. Anticipated economic benefits: After its completion the project will realize annual sales income of 60 million yuan, with profit of 8 million yuan, tax payment of 4 million yuan, and investment recovery period of 6 years.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

13  Sunflower seeds deep processing project with annual production of 200,000 tons

1. Total investment in the project: 176.34 million yuan

2. Location of the construction site: Nong’an Industrial Cluster, inChangchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of45,000 m2for construction of sunflower oil production lines and supporting infrastructure, and will annually deep-process 200,000 tons of sunflower seeds.

5. Anticipated economic benefits: After its completion the project will realize annual sales income of 806.19 million yuan, with profit of 383.51 million yuan, and tax payment of 31.21 million yuan.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

14  Project with annual production of 6,000 tons of goose series products

1. Total investment in the project: 100 million yuan

2. Location of the construction site: Nong’an Industrial Cluster, inChangchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Annually producing 6,000 tons of goose series products.

5. Anticipated economic benefits: After its completion the project will realize annual sales income of 200 million yuan, with profit of 20 million yuan, tax payment of 10 million yuan, and investment recovery period of 5 years.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

15  Tomato deep processing project annually processing 120,000 tons of tomatoes

1. Total investment in the project: 204.8836 million yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: The project annually processes 120,000 tons of tomatoes, and can obtain annual production of 22,500 tons of tomato sauce and 15,000 tons of tomato juice. The project includes a total of 15 buildings and structures, with total floor area of9,288 m2, land occupation of8,672 m2.

5. Anticipated economic benefits: The annual sales income can reach up to 272,320,500 yuan, with net profit of up to 26,946,900 yuan, and investment recovery period of 4.15 years.

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

16  Carrot deep processing project annually processing 100,000 tons of carrots

1. Total investment in the project: 156,227,600 yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Annually processing 100,000 tons of carrots to obtain the products of 20,000 tons of carrot sauce and 50,000 tons of carrot compound juice. The project includes a total of 21 buildings and structures, with total floor area of22,038 m2.

5. Anticipated economic benefits: Annual sales income will reach 283,173,300 yuan, with net profit of up to 31,586,800 yuan, and investment recovery period of 5.44 years (after tax, including construction period)

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

17  Soybean comprehensive deep-processing project annually processing 650,000 tons of soybeans

1. Total investment in the project: 445 million yuan

2. Location of the construction site: Song village, Fufeng town, Chaoyang district,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of300,000 m2, with floor area of33,000 m2, and will have total production capacity of processing 2,000 tons of soybeans per day (650,000 tons per year). The output will be 320 tons/day of soybean oil meeting national standard, 1,600 tons/day of soybean dregs, and 120 tons/day of phospholipids.

5. Anticipated economic benefits: Annual sales income of 750 million yuan, profit of 75.6 million yuan, and investment payback period of 5.7 years.

6. Contacts: Zhang Bo, Zhai Yunfei, Ding Lin

7. Tel: 0086-431-5109189, 5109113, 18943190288

 

18  Potato industrialization project annually processing 1 million tons of potatoes

1. Total investment in the project: 437,855,500 yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: According to the overall planning of the project, 1 million tons of potatoes will be processed each year, expected annual production include 100,000 tons of potato flakes, 50,000 tons of frozen French fries, 8,000 tons of potato crisps, and 100,000 tons of fresh potatoes.

5. Anticipated economic benefits: Annual sales income can reach up to 303,255,300 yuan; net profit can reach up to 68,111,300 yuan; the investment recovery period will be 5 years (including construction period of 1 year).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

19  Project annually processing 3 million pieces of cow hide

1. Total investment in the project: 5 billion yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of350,000 m2, with floor area of200,000 m2.

5. Anticipated economic benefits: After reaching designed capacity, the annual output value will be 120 million yuan, with annual profit of 10 million yuan, tax payment of 10 million yuan, and investment recovery period of 7 years.

6. Contact: Xie Hong

7. Tel: 0086-431-87806877

 

20  Project annually slaughtering and processing 200,000 heads of mutton sheep

1. Total investment in the project: 57 million yuan

2. Location of the construction site: Yushu Huancheng Industrial Cluster, inJilinprovince

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: Annually slaughter and process 200,000 heads of mutton sheep.

5. Anticipated economic benefits: After reaching the designed capacity, the project will realize annual sales income of 62 million yuan, with profit of 7.8 million yuan, and tax payment of 1.5 million yuan.

6. Contact: Zhang Guoxin

7. Tel: 0086-431-83863000

 

21  Rice straw and rice husk processing project for comprehensive utilization

1. Total investment in the project: 375 million yuan

2. Location of the construction site: Dehui,Changchun

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Annual production of150,000   m³of high density board made from rice straw, and 60,000 tons of silica white obtained from rice husks.

5. Anticipated economic benefits: Annual sales income will reach up to 540 million yuan; net profit will reach up to 118.31 million yuan. The investment recovery period will be 3.4 years (including construction period).

6. Contacts: Zhang Zhenbo, Wang Hongtao

7. Tel: 0086-431-87223510, 81183399

 

22  Sika deer series tonic production project

1. Total investment in the project: 40 million yuan

2. Location of the construction site: Clean Industrial Park, Changchun Shuangyang Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of10,000 m2, with floor area of8,000 m2, and will annually output 500 tons of nourishing health wine.

5. Anticipated economic benefits: Annual sales income of 280 million yuan; realized profit of 50 million yuan.

6. Contact: Zhang Dong

7. Tel: 0086-431-84152268

 

23  Project for production of liquid-polypeptide protein milk

1. Total investment in the project: 100 million yuan (including 100 million yuan financing)

2. Location of the construction site: Northeast Core Area of Changchun High-Tech Industrial Development Zone

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: An estimated10,000 m2area of plant construction and equipment installation.

5. Anticipated economic benefits:

Expected annual revenue of the project is 300 million yuan, with total profit and tax of 90 million yuan, and investment recovery period of 1 year.

6. Contact: Wang Yu

7. Tel: 0086-431-87019007, 13844076609

 

24  Industrialization project of collagen peptide made from Changbai Mountain rana skin

1. Total investment in the project: 30 million yuan

2. Location of the construction site: Changchun National High-Tech Industrial Development Zone

3. Method of cooperation: joint venture

4. Construction contents and scale:

One production line for rana skin comprehensive utilization will be built in this project, with annual production of10,000 kgof collagen protein peptide made from rana skin.

5. Anticipated economic benefits:

Annual revenue of 80 million yuan; total profit of 24 million yuan; expected investment recovery period of 2 years (including construction period).

6. Contact: Han Yang, Liu Guanchuan

7. Tel: 0086-431-85542429

 

 

IV. Modern Service Industry Projects (25)

 

1  Grain storage and logistics base construction project

1. Total investment in the project: 994 million yuan (including 700 million yuan financing)

2. Location of the construction site: Northeast Core Area of Changchun High-Tech Industrial Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale:

The project covers an area of500,000 m2, with floor area of350,000 m2, planning to build 16 horizontal storehouses and 24 low-temperature storehouses, with a total storage capacity of 542,000 tons.

5. Anticipated economic benefits:

After achievement of designed capacity, the annual sales income will be 3.256 billion yuan, with total profit of 115 million yuan and investment recovery period of 8.5 years.

6. Contact: Huang Qingkai

7. Tel: 0086-431-85542528, 15843071967

 

2  Eastern Changchun business headquarters project

1. Total investment in the project: 1.2 billion yuan

2. Location of the construction site: Leisure and business development area (inside Yingjun town, on both sides of the extension line ofJilin Roadto the east) in Erdao district,Changchuncity

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: The project covers an area of50,000 m2, to build office buildings and high-end business headquarters with expected floor area of120,000 m2.

5. Anticipated economic benefits: The project site is closely next to and on both sides of the extension line ofYingbin Avenue–Jilin Roadto the east which leads toLongjiaInternationalAirport. It is a window showingChangchun's future development toward the east to link up with the world. Under the joint efforts of the Erdao district and the municipal government, the construction of the section of theJilin Roadextension line in Erdao district has been completed. Meanwhile, administrative center of Erdao district move toward the east and will certainly actuate the region's economic development. Construction of high-end business headquarters or offices here certainly has considerable future economic benefits.

6. Contact: Liu Xingyan

7. Tel: 0086-431-84646772

 

3  Jicai historic streets commercial construction project

1. Total investment in the project: 2.25 billion yuan

2. Location of the construction site: Dongzhan neighborhood (east of Jishun Street, west of Dongsheng Street, south of Fufeng Road, north of Rongguang Road), Erdao district, Changchun city

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: The project covers an area of85,000 m2. To build an industrial base similar toBeijing798 or Shenzhen OCT (OverseasChineseTown), which integrates dining, bars, and cultural creativities.

5. Anticipated economic benefits: The project is bound to play an active role in enriching the cultural life of the residents in the area, accelerating regional development, promoting employment, and improving people's living standards.

6. Contact: Liu Xingyan

7. Tel: 0086-431-84646772

 

4  Financial services outsourcing project

1. Total investment in the project: 1 billion yuan

2. Location of the construction site: West Part Commercial Cluster of Changchun Jingyue Development Zone

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: the project covers an area of20,000 m2, with floor area of80,000 m2, mainly to build financial BPO mansion and supporting service facilities.

5. Anticipated economic benefits: After completion, the project will have annual output value of 500 million yuan, with annual profit and tax of 150 million yuan, and is expected to recover the cost in 10 years.

6. Contact: Chen Huaibo

7. Tel: 0086-431-84533752

 

5  Modern dining and entertainment cultural street construction project

1. Total investment in the project: 500 million yuan

2. Location of the construction site: to the both sides ofB-14 Roadin the west part of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: The project covers an area of about50,000 m2, striving to build a block of modern dining and entertainment cultural streets integrating shopping and dining, living facilities, entertainment and other functions in one.

5. Anticipated economic benefits: After completion of the project, the block is expected to achieve annual revenue of about 300 million yuan, with annual profit of about 150 million yuan, and investment recovery period of 4 years.

6. Contacts: Wang Dan, Liu Li

7. Tel: 0086-431-84532420

 

6  International Business Headquarters construction project

1. Total investment in the project: 4.5 billion yuan

2. Location of the construction site: east side of the central axis of the Western New Area of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: The project covers a total area of about200,000 m2, with total floor area of900,000 m2, mainly to build high-grade office buildings, shopping malls, star hotels and residential apartments, performing complex functions of business office, international conference, commercial lodging, shopping, dining, entertainment, and etc.

5. Anticipated economic benefits: Annual revenue of RMB 1.5 billion yuan; total profit of RMB 500 million yuan; investment recovery period of 3 years.

6. Contacts: Ding Xiaohong, Jin Meichen

7. Tel: 0086-431-84532421

 

7  Project for construction of a luxury international hotel

1. Total investment in the project: 2 billion yuan

2. Location of the construction site: Modern Ecological New City (east of Linhe Street, north of Fuzhi Road, west of Linhedong Street) in the west part of Changchun Jingyue Development Zone

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: Planned project covers a total land area of about50,000 m2, with a total floor area of about400,000 m2(including underground), and building height of approximately100 meters.

5. Anticipated economic benefits: After completion, annual revenue of the project will be about RMB 1.8 billion yuan, with total profit of about RMB 200 million yuan, and investment recovery period of about 10 years.

6. Contacts: Wang Jun, Liu Li

7. Tel: 0086-431-84532420

 

8  Project for construction of Northeast Asia International Financial Mansion

1. Total investment in the project: 1.2 billion yuan

2. Location of the construction site: the western New Area of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: According to planning, the project covers land area of50,000 m2, with floor area of up to200,000 m2. The project consists of three relatively independent but mutually connected high-rise buildings, integrating offices, banking hall, and necessary facilities for banks.

5. Anticipated economic benefits: After full completion of the project, the annual revenue is expected to be 320 million yuan, with annual total profit of 180 million yuan, and investment recovery period of about 5 to 7 years.

6. Contacts: Liu Junfeng, Wang Dazhi

7. Tel: 0086-431-85828798

 

9  Project for construction of Town Plaza Commercial Complex

1. Total investment in the project: 3 billion yuan

2. Location of the construction site: south part (east ofXiantai Street, northofWeixing Road) of Changchun Economic and Technological Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: The project covers land area of17 hectares, according to the current planning, the total floor area is approximately570,000 m2, including approximately120,000 m2of residential buildings above the ground and450,000 m2of commercial buildings.

5. Anticipated economic benefits: Sales revenue will reach RMB 1.5 billion yuan, with annual profits of RMB 300 million yuan.

6. Contact:YaoHongbo

7. Tel: 0086-431-84617678

 

10  Project for construction of sports and supporting facilities in South New City

1. Total investment in the project: 500 million yuan

2. Location of the construction site: north of the Fourth Ring Road, in South New City, in South Metropolis Economic Development Zone, in Nanguan district,Changchuncity

3. Method of cooperation: overall remising and collaborative development

4. Construction contents and scale: the land is used for sports purpose, with planned land area of47,000 m2. The floor area ratio is 1, so that the planned floor area is also approximately47,000 m2.

5. Anticipated economic benefits: According to the planning, future resident population in theSouth New Citywill reach 300,000. Plus the floating population, the population size will be 500,000. The future high-end residential population in the South Changchun New City will have great demand for sports and fitness. The project is just located in the center of the core area of the South Changchun New City, a super-excellent site for construction of large-size stadium, gymnasium, fitness center and other sports facilities.

6. Contact: Sun Huan

7. Tel: 0086-431-89995066

 

11  Project for construction of medical and health care facilities in South New City

1. Total investment in the project: 940 million yuan

2. Location of the construction site: east of Nanhu Central Street, south of the Fourth Ring Road, in South Metropolis Economic Development Zone, in Nanguan district, Changchun city

3. Method of cooperation: overall remising and collaborative development

4. Construction contents and scale: Giving priority to medical facilities, build health care system facilities which integrates Class A hospital, pension rehabilitation center, recreational sports facilities, health and epidemic prevention, first aid, and etc. The estimated construction period is 3 years. The project covers land area of94,000 m2, with floor area ratio of 2, and gross floor area of about188,000 m2.

5. Anticipated economic benefits: The construction of the project will bring favorable social benefits in addition to bringing economic benefits for the enterprises. Its construction can spur the economic development of the surrounding areas, promote employment, and promote the economic development ofChangchuncity. Development and construction of the project will drive regional economic growth, drive hygiene and health consumption of the New City residents, improve hygiene and health facilities of the residents, improve urban residents’ health level, meet people’s health and welfare requirements, and will bring the stability of society, promote the development of urban spiritual civilization.

6. Contact: Sun Huan

7. Tel: 0086-431-89995066

 

12  Project for construction of trading market for Chinese deer products wholesale

1. Total investment in the project: 100 million yuan

2. Location of the construction site: Clean Industrial Park, Changchun Shuangyang Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project covers land area of25,000 m2, with floor area of45,000 m2, and will mainly distribute and sell by bulk deer raw products, deer deep processed products, deer feed, deer using veterinary drugs, and Jilin native and specialty products, concurrently do business in health food, green food, tourist souvenirs, dining and entertainment, warehousing, and so on.

5. Anticipated economic benefits: Annual sales income of 126.3 million yuan; realized profit of 66.4 million yuan.

6. Contact: Zhang Dong

7. Tel: 0086-431-84152268

 

13  Project for construction of “Morality, Care, and Piety” Pension Services Village

1. Total investment in the project: 12 billion yuan

2. Location of the construction site: between West Third Ring Road and West Fourth Ring Road, in Changchun Economic and Technological Development Zone

3. Method of cooperation: joint venture

4. Construction contents and scale:

The project covers land area of 3.8 square kilometers and will base on the spirit of “carrying forward filial piety, services for the elderly, development of people's livelihood, contributing to society”, create the most ecological, healthy retirement village. The project is positioned as a domestic first-class high-end health-preserving and pension services industry base, to develop low-carbon, green, and sustainable new type modern service industry. The project will take medium to high end health preserving and pension services industry as the core business, rely on the support of advanced clinical techniques, utilize the resources advantage of the natural environment of Yanminghu lake original ecology, target the medium to high end group as client resources, to create a modern high end service industry base integrating health preserving, pension services, tourism and vacation, rehabilitation, and medical care and services. The Pension Services Village project will focus on creating a “garden”, a “yard”, and seven service centers, to meet the basic needs of the elderly residents of the community as well as various special physiological, psychological and social needs of the elderly, in order to enrich their living activities and improve their quality of life.

 5. Anticipated economic benefits: Estimated annual revenue of 1 billion yuan; total profit of 300 million yuan; investment recovery period of around 10 to 15 years.

6. Contact: Li Yang

7. Tel: 0086-431-89625156

 

14  Tianchi commercial complex construction project

1. Total investment in the project: 1.4 billion yuan

2. Location of the construction site: east ofChangbai   Highway, northof West Third Ring Road, south of the airport-dedicated railway, the range inside the angle of the new inter-city high-speed rail, in Changchun Lvyuan Economic Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: proposed planning and construction of large commercial complex integrating freight transportation, logistics, commercial, financial, residential, and parking.

5. Anticipated economic benefits: 280 million yuan

6. Contacts: Wang Hong, Wang Xuehui

7. Tel: 0086-431-89625197

 

15  Project for construction of livestock trading market

1. Total investment in the project: 2 billion yuan

2. Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3. Method of cooperation: contractual cooperation, joint venture

4. Construction contents and scale: The project occupies a total land area of800,000 m2, with floor area of150,000 m2.

5. Anticipated economic benefits: After reaching the designed capacity, the annual output value will be 1.2 billion yuan, with annual profit of 300 million yuan, and investment recovery period of 1 year.

6. Contact: Xie Hong

7. Tel: 0086-431-8780687

 

16  Project for construction of pepper, garlic, and onion trading market

1. Total investment in the project: 31.59 million yuan

2. Location of the construction site: Halahai town, Nong’an county,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Construct a trading market of pepper, garlic, and onion (“the three hot vegetables in northeastChina). Plan to build trading greenhouses of20,000 m2, repositories and low temperature preservation storehouse of30,000 m2.

5. Anticipated economic benefits: After the completion of the project, the annual sales income will reach 18 million yuan, with profit of 7.44 million yuan, tax payment of 910,000 yuan, and investment recovery period of 4.7 years.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

17  Project for construction of West New City urban complex

1. Total investment in the project: 2 billion yuan

2. Location of the construction site: west of the planned West Road, south of Dongfeng Street, east of Dazhong Street, north of Linyin Boulevard, in Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: underwrite land leveling costs in the early stage, and obtain land use rights through bidding, auction, or listing.

4. Construction contents and scale: The construction covers land area of11.72 hectares(planned floor area ratio of 1.5 to 2.5).

5. Anticipated economic benefits: annual profit of about 200 million yuan; investment recovery period of 10 years.

6. Contact: Liu Xiangdong

7. Tel: 0086-431-81501613

 

18  Project for construction of West New City star hotel

1. Total investment in the project: 800 million yuan

2. Location of the construction site:Auto Vehicle   Squarein Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Construct five-star hotels, covering land area of10,000 m2, with floor area of40,000 m2.

5. Anticipated economic benefits: sales income will reach 500 million yuan, with profit of RMB 50 million yuan.

6. Contact: Cui Kai

7. Tel: 0086-431-81501730

 

19  Project for construction of large-size supermarket in West New City

1. Total investment in the project: 900 million yuan

2. Location of the construction site: within the boundaries of north of Nanyang Road, south of the Commercial College, west of Heping Street, east of Guihuan Road, in Phase V of Dazhong Garden, in Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Construct a large-size supermarket, covering land area of87,000 m2, with floor area of300,000 m2.

5. Anticipated economic benefits: sales income will reach 2 billion yuan, with profit of RMB 100 million yuan.

6. Contact: Cui Kai

7. Tel: 0086-431-81501730

 

20  Project for construction of home appliances logistics center

1. Total investment in the project: 1 billion yuan

2. Location of the construction site:LanjiaIndustrialLogisticsPark, in Kuancheng district,Changchuncity

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: The project covers land area of300,000 m2, major constructions in Phase I including trading market of high-end home appliances, E-commerce center, system integrated development and design, home appliances exhibition hall, large order meeting reception, warehousing and distribution logistics, life services, public facilities and supporting projects, etc.

5. Anticipated economic benefits: After the project is completed, the estimation in accordance with the overall vision and business model is that the annual sales income will be 1.36 billion yuan, with profits of 272 million yuan.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

21  Project for construction of commercial complex in administrative center of Changjiang Road

1. Total investment in the project: 8 billion yuan

2. Location of the construction site:

North of the Beltway, west ofNorth Kaixuan   Road, eastofChangnong Road, both sides ofBeixing Road, in Kuancheng district,Changchuncity

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale:

The project covers land area of 1 million square meters, with commercial floor area ratio of 4.0, and residential floor area ratio of 1.5-2.5, mainly to build a commercial complex integrating multiple functions of commerce and trade, culture, finance, leisure, entertainment, office, and living.

5. Anticipated economic benefits:

The plot is suitable for both living and business because of its ideal geographic location, consummate city facilities, convenient transportation, and beautiful environment. This area will become the new administrative center of Changjiang Road Development Zone, gathering large flow of people, logistics, information, and capital, rendering abundant business opportunities.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

22  Project for construction of commercial complex between the Third and the Fourth Ring Road (on both sides of North Renmin   Street)

1. Total investment in the project: 650 million yuan

2. Location of the construction site:

East of C-7 Street, west ofC-8 Street, southofC-9 Road, on both sides ofNorth Renmin   Street, in Kuancheng district,Changchuncity

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale:

The project covers land area of115,000 m2, mainly to build a commercial complex integrating multiple functions of trade, high end office building, finance, leisure, and etc. with floor area ratio not less than 2.0.

5. Anticipated economic benefits:

The project has ideal geographic location, beautiful environment, convenient traffic, for it is closely adjacent to the administrative center of Kuancheng district and theForest Park. By investing in the development of commercial real estate projects here, the room for market value improvement is vast and can bring huge economic benefits for developers.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

23  Project for construction of Northeast Asia digital logistics park

1. Total investment in the project: 5 billion yuan

2. Location of the construction site:JilinProvincePhotoelectricInformationIndustryPark, in Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: the digital dispatching control center covers land area of about90,000 m2, the goods regulatory inspection base covers land area of about50,000 m2, the storage center covers land area of about1,500,000 m2, the logistics sorting and distribution center covers land area of about1,000,000 m2, the digital government center covers land area of about60,000 m2, and the vehicle deployment base covers land area of about300,000 m2.

5. Anticipated economic benefits: The Northeast Asia digital logistics park relies on the strategic location of Jilin Province, targeting Northeast Asia, and serving Changchun-Jilin-Tumen, integrating the resources, combining with aviation, railway, civil, and port, to create a comprehensive, three-dimensional one-stop digital logistics hub. After the completion of the whole park, expected annual revenue will be up to RMB 8-12 billion yuan, with total profit of about 2-4 billion yuan, and investment recovery period of about 5-8 years.

6. Contacts: Ding Xiaohong, Sui Minglu

7. Tel: 0086-431-84532421

 

24  Large online supermarket and entity supermarket joint operation project

1. Total investment in the project: 30 million yuan

2. Location of the construction site: No.286 Torch Road, Changchun High-tech Zone

3. Method of cooperation: joint venture

4. Construction contents and scale: Preparation of the project has been completed, and operational period embarked. After 3 years, daily web site flow is expected to reach 300,000 or more IP per day, and order processing capacity can reach more than 30,000 orders per day, with sales orient toward the whole country, while preparing and delivering goods for up to 4,000 entity supermarkets, based on Changchun as the core of development.

5. Anticipated economic benefits: After 3 years, the annual turnover is expected to reach above 1 billion yuan, with total profit of above 50 million yuan.

6. Contact: Teng Hongyan

7. Tel: 0086-431-81076800

 

25  Project for construction of E-commerce Entrepreneurship Incubation Park

1. Total investment in the project: 300 million yuan

2. Location of the construction site: No.286 Torch Road, Changchun High-tech Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: the project covers land area of10,000 m2, with gross floor area of50,000 m2, mainly to build E-commerce corporate offices, andIncubationPark.

5. Anticipated economic benefits: The investment recovery period is three years. Annual turnover is estimated to reach above 10 billion yuan, with annual profits and taxes of above 200 million yuan, and total annual profit of above 50 million yuan.

6. Contact: Teng Hongyan

7. Tel: 0086-431-81076800

 

 

V. Cultural Industry Projects (15)

 

1  Project for construction of Eurasian culture and art exhibition and trade center

1. Total investment in the project: 80 million yuan

2. Location of the construction site: Changchun Eurasia sales fields

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: Utilizing the1,500 m2of foundation at the site, gradually introduce items such as painting and calligraphy exhibition, antique auction, appreciation, book display, wholesale, folk art production, training, sales, etc., to form an exhibition and trade place for a complete range of cultural and art works. Plans to use about three years time to expand the business area to 30,000-50,000 m2, forming an art works trading center oriented toward the province and influencing the wholeNortheast China. Items include exhibition of painting and calligraphy, antique auction, appreciation, book display, wholesale, folk art production, training, sales, etc.

5. Anticipated economic benefits: Annual revenue of 30 million yuan, tax payment of 2 million yuan.

6. Contact: Zhang Bo

7. Tel: 0413-85109322

 

2  Project for construction of animation theme amusement park

1. Total investment in the project: 1 billion yuan

2. Location of the construction site: The New Area in the west part of Changchun Jingyue Development Zone

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale:

The project is expected to cover total land area of about200,000 m2, on which to build facilities including the cartoon experience and show area, science-fiction experience and show area, digital film base, digital animation base, originality base, Fantawild film and television theme park, film and television shooting base, cultural derivatives base, games and educational software base, culture and technology vocational training base, exhibition center, flying theater, theme hotels, etc.

5. Anticipated economic benefits:

After completion, the project will have annual output value of RMB 500 million yuan, with annual profits and taxes of RMB 150 million yuan. The cost is is expected to be recovered within ten years.

6. Contact: Chen Huaibo

7. Tel: 0086-431-84533752

 

3  Project for construction of Ruiyun Valley cloud computing center

1. Total investment in the project: 600 million yuan

2 Location of the construction site: software and service outsourcing industry base, inOptoelectronicInformationIndustrial Park, in the New Area in the west part of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: The project is planned to cover land area of50,000 m2, constructions including cloud computing services center, data storage center, R&D center, etc.

5. Anticipated economic benefits: After full completion of the project, annual revenue is expected to reach 120 million yuan, with total annual profit of 80 million yuan, and investment recovery period of 6 to 8 years.

6. Contacts: Liu Junfeng, Zhang Yufei

7. Tel: 0086-431-85828798

 

4  Project for construction of a town for urban tourism, leisure, and vacation

1. Total investment in the project: 2.4 billion yuan

2. Location of the construction site: the west part of Changchun Jingyue Development Zone

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: The project covers land area of200,000 m2, with gross floor area of250,000 m2. Planning to build a leisure and vacation village to serve tourism, entertainment, and conference receptions purposes, and will integrate items such as lodging, dining, bathing, fishing, etc. In this project, a new star hotel will be built, equipped with business rooms and standard rooms, Chinese and Western restaurants, entertainment area, and multi-functional conference hall; and a villa-cluster with a column of small wooden houses will be built, equipped with recreational fishing, bathing, water sports and entertainment, and dining facilities.

5. Anticipated economic benefits: After completion, the project will have annual output value of RMB 1.2 billion yuan, with annual profit of RMB 200 million yuan, and estimated investment recovery period of 10 years.

6. Contact: Chen Huaibo

7. Tel: 0086-431-84533752

 

5  Project for construction of cultural facilities in South New City

1. Total investment in the project: 1.03 billion yuan

2. Location of the construction site: south of the Fourth Ring Road, in South Metropolis Development Zone, in Nanguan district,Changchuncity

3. Method of cooperation: overall remising and collaborative development

4. Construction contents and scale: focusing on cultural elements, to construct a project for cultural and recreational activities, which integrates cultural and artistic creativity, exchanges, exhibitions, performing arts, and a large theater. The estimated construction period is 3 years. The project covers land area of103,000 m2, with floor area ratio of 2, and gross floor area of about206,000 m2.

5. Anticipated economic benefits: After the project is completed and put into production, the gathering of major cultural facilities, stadiums, etc. will create annual output value of more than 1 billion yuan, with profit of more than 100 million yuan, and investment recovery period of 3 to 5 years.

6. Contact: Sun Huan

7. Tel: 0086-431-89995066

 

6  Project for construction of 3G network real-time traffic information platform

1. Total investment in the project: 50 million yuan

2. Location of the construction site: the south part of Changchun National High-Tech Industrial Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: research and development of software, and establishment of network platform

5. Anticipated economic benefits: With the development progress of the project, the annual revenue will reach 20 million yuan within 3 years; and after that, the annual revenue will be stabilized at the level of 20 million yuan with profit margin of 50%. Cost of investment will be recovered within 5 years.

6. Contact: Han Yang, Liu Guanchuan

7. Tel: 0086-431-85542429

 

7  Project for construction of China Jilin - Northeast Asia Cultural and Creative Technology International Park

1. Total investment in the project: 500 million yuan

2. Location of the construction site: Jinhe Street No.155, Changchun National High-Tech Industrial Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale:

Planning and construction of an international cooperation park covering100,000 m2.

5. Anticipated economic benefits:

The annual output value will exceed 130 million yuan, with total annual profit of more than 100 million yuan, and investment recovery period of 5 years.

6. Contact: Wang Haibo

7. Tel: 0086-431-85542491, 13086882676

 

8  Project for construction of an animation incubation base

1. Total investment in the project: 150 million yuan

2. Location of the construction site: the western EBD area of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale:

The project includes animation production, research and development office and its designed subsidiaries. Major products of the animation base are cartoon TV programs, animation movies and online games, with annual production of 35 million minutes of various animation products.

5. Anticipated economic benefits: After completion, the project will generate annual income of 500 million yuan.

6. Contact: Wang Dan

7. Tel: 0086-431-84532420

 

9  Project for construction of a digital entertainment industry base

1. Total investment in the project: 150 million yuan

2. Location of the construction site: the western EBD area of Changchun Jingyue Economic Development Zone

3. Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation

4. Construction contents and scale: Office and research facilities for digital media research, development, entrepreneurship, and services; in specific, including the online games incubation center, mobile games research and development center, digital industry information center, training center, animation center, digital trading center, and games testing and promotion center.

5. Anticipated economic benefits: After reaching the designed capacity, the project will have annual output value of up to 500 million yuan.

6. Contact: Wang Dan

7. Tel: 0086-431-84532420

 

10  Project for construction of a culture industrial park

1. Total investment in the project: 2.5 billion yuan

2. Location of the construction site:

From Yatai North Street in the east, to Jiutai Road in the west; from Tiebei 2nd Road in the south, to Taibei Street in the north.

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale:

The project covers land area of about200,000 m2, planning to build a cultural industrial park focusing on Northeast China customs and styles while integrating film theater, animation presentation, technology demonstration, and children's activities.

5. Anticipated economic benefits:

This plot is located next toKuanchengWandaPlazaand Redstar Macalline Furnishings Complex. Along with the commencing of construction of Changchun three-dimensional transfer center, Subway Line 1, Kuan Wanda Plaza, and Redstar Macalline Furnishings Complex, here will gather large crowds, logistics, capital flow, and information flow, bringing abundant commercial opportunities, and can bring huge economic benefits for investors after the completion of the project.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

11  Project for construction of Hongqi Forest Wetland Park

1. Total investment in the project: 300 million yuan

2. Location of the construction site: Helong village, Lanjia town, Kuancheng district,Changchuncity

3. Method of cooperation: wholly foreign-owned, Building-Transferring (BT), Building-Operating-Transferring (BOT), etc.

4. Construction contents and scale:

The project covers land area of about1,000,000 m2, relying on the water system resources of Hongqi Reservoir, to develop and construct a forest wetland park, improve supporting facilities of the park, change the humanistic environment, and provide a place for leisure, entertainment for the people in surrounding areas. Positioning: an ecological, natural, and people-oriented district-level park

5. Anticipated economic benefits:

After completion, the park can not only improve the water quality of Hongqi Reservoir, but also change the humanistic environment, modify the urban landscape, increase the value of surrounding residential land, rendering high social benefits.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

12  Project for construction of an all-citizens fitness center

1. Total investment in the project: 125 million yuan

2. Location of the construction site: from Yatai North Street in the east, to Guihua Road in the west; from Guihua Road in the south, to North Third Ring Road in the north, in Kuancheng district, Changchun city

3. Method of cooperation: Joint venture, contractual cooperation, BT, and other methods

4. Construction contents and scale:

This plot covers land area of29,000 m2, with floor area of23,000 m2, According to planning, 4 floors above the ground and 1 underground floor will be built, mainly including construction of spaces for various sports activities, rooms for sports and entertainment, parking lot, etc.

5. Anticipated economic benefits:

The fitness center is a public welfare project, which can improve the living environment of residents and enhance urban services functions. Projects such as Changchun subway Line 1, Middle East Modern Life Town Plaza, and Xiwang Center commercial complex begin their construction, the residential plots such as Zhengda Guangming City, Wuzhong Impression, Zhongzhi Blue City, Britain Small Town, etc. begin to take shape, and the administrative center of North Changchun New City has been formed, so that massive people and materials flow to here. After completion of this project, its annual turnover is estimated at 9 million yuan, with profits and taxes of 2 million yuan.

6. Contacts: Fu Deyong, Sun Jianbo

7. Tel: 0086-431-89990273

 

13  Project for construction of Chun Tong Townlet

1. Total investment in the project: 1 billion yuan

2. Location of the construction site: West New City Development District, in Lvyuan district

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: The project occupies land area of200,000 m2, to create a paradise – the “Chun Tong Townlet” – for the children in Changchun city, which will integrate Happy Kindergarten, children's entertainment world, Dream Science Museum, Simulation Life, etc.

5. Anticipated economic benefits: This project is undertaken for public good.

6. Contact: Yang Biao

7. Tel: 0086-431-87081608

 

14  Project for construction of “two parks and one green belt” in West New City

1. Total investment in the project: 595 million yuan

2. Location of the construction site: West New City Development District, in Lvyuan district,Changchuncity

3. Method of cooperation: wholly foreign-owned

4. Construction contents and scale: The project covers total land area of1,340,000 m2, includingXinglonghuLakeof300,000 m2, Green Belt Corridor of150,000 m2, andTongxinhuLakeof890,000 m2. Based on the natural water bodies of the two lakes, build an urban waterscape park with metropolitan characteristics, and form an all-weather leisure and entertainment space.

5. Anticipated economic benefits: This project is undertaken for public good.

6. Contact: Yang Biao

7. Tel: 0086-431-87081608

 

15  Project with Ganli color-printing and packaging products

1. Total investment in the project: 50 million yuan

2. Location of the construction site: Changchun Cultural Printing Industry Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: New workshop, office building, etc., with gross floor area of6,000 m2, including factory building of3,500 m2; office building of1,500 m2. Purchase 22 units/sets of equipment. Annual production of 2 million square meters of packaging cartons.

5. Anticipated economic benefits: The annual sales income will be 80 million yuan, with total annual profit of 15 million yuan, and investment recovery period of 6 years (before tax).

6. Contact: Hong Jiqian

7. Tel: 13514488999

 

 

VI. Strategic Projects of Emerging Industry (18)

 

1  Project of State Class A fireproof material production

1.Total investment in the project: 217.28 million yuan

2.Location of the construction site: North Sector of Changchun Jiutai Economic Development Zone

3.Method of cooperation: joint venture

4.Construction contents and scale: Construction of the facilities for producing new fireproof insulation board for external wall. Construction of new factory building and office with gross floor area of65,672 m2, which includes factory building (44,386 m2), warehouse (9,654   m2), office building (5,612   m2), and so on.

5.Anticipated economic benefits: annual sales income of 172.5 million yuan, annual total profit of 13.8 million yuan, and investment recovery period of 15 years.

6.Contact: Wang Chunyu

7.Tel: 13341484448

 

2  Project with annual output of 9 million linear meters of anticorrosion and waterproof material

1. Total investment in the project 100 million (including 60 million financing)

2. Location of the construction site: Northeast Core Area of Changchun National High-Tech Industrial Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: The project plans to cover an area of10,000 m2, construct factory buildings, office buildings, warehouse, other production and ancillary facilities, etc. Annual output of 9 million linear meters anticorrosive and waterproof felt.

5. Anticipated economic benefits: After the completion of the project and reaching the designed capacity, it will realize output value of 300 million yuan, profit of 50 million yuan, investment recovery period of 3~4 years.

6. Contact: Wu Qingjun

7. Tel: 0086-431-87019013, 13944190222

 

3  Project with annual output of 300,000 tons of renewable energy

1.Total investment in the project: 800 million yuan

2.Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project covers a total area of228,000   m2, with floor area of150,000 m2. Construction of factory buildings of120,000 m2and office buildings of30,000   m2.

5.Anticipated economic benefits: After reaching designed capacity, it can realize annual output value of 1 billion yuan, annual profit of 200 million yuan, tax payment of 50 million yuan and investment recovery period of 6.3 years.

6.Contact: Xie Hong

7.Tel: 0086-431-87806877

 

4  Construction project of renewable material recycling center

1.Total investment in the project: 86.65 million yuan

2.Location of the construction site: ChangMing village, Pinghu sub-district office, Shuangyang district,Changchuncity.

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: Construction of 25 new recycling pavilions with each covering a floor area of15 m2and the total floor area will be375 m2. Construction of 60 new storehouses for renewable material recycling with each covering a floor area of800 m2, and the total floor area will be48,000 m2. Construction of a distributing room of15 m2which is solely composed of color plate and an office building facing the street which is composed of two floors of brick structure. Scale of the construction includes an occupation of area of60,000   m2and total floor area of50,790   m2.

5.Anticipated benefits: Annual sales income of 114.94 million yuan, total profit of 20.76 million yuan, annual tax payment of 5.19 million yuan and investment recovery period of 1 year.

6.Contact:Cao Zhanshang

7.Tel: 0086-431-84232006

 

5  Project with annual output of 0.3 million tons of straw diesel

1.Total investment in the project: 860 million yuan

2.Location of the construction site: northeast core area of Changchun National High-Tech Industrial Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project covers an area of70,000   m2and floor area of50,000 m2for the purpose of constructing factory buildings, warehouses and office buildings, etc. And will reach the goal of annual output of 0.3 million tons of straw diesel.

5.Anticipated economic benefits: Average annual sales income of 855,2734 million yuan, average tax payment of 89,8465 million yuan, average annual after-tax profit of 269,5395 million yuan, and investment recovery period of 4 years.

6.Contact:Cao Wanli

7.Tel: 0086-431-85542548, 15843071907

 

6  Project with annual output of 0.5 million tons of M50 methanol gasoline

1.Total investment in the project: 650 million yuan

2.Location of the construction site: Nong’an Industrial Cluster, in Nong’an county,Changchuncity

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project plans to utilize266,000   m2of land and the floor area will be152,000   m2. The annual output of M50 methanol gasoline will be 0.5 million tons.

5.Anticipated economic benefits: After the completion of the project, it can realize sales income of 3.25 billion yuan, profit of 982.4 million yuan and tax payment of 324.19 million yuan.

6.Contact: Wang Deyou

7.Tel: 0086-431-83220871

 

7  Project with annual output of 0.5 million units of Lucida series terminal products

1.Total investment in the project: RMB 70.33 million yuan

2.Location of the construction site: Changchun Economic and Technological Development Zone

3.Method of cooperation: joint venture

4.Construction contents and scale: Establish production capacity for annual production of 0.5 million Cloud terminals.

5.Anticipated economic benefits: Annual sales income of 221 million yuan, net profit of 25.09 million yuan, investment recovery period (including the construction period) of 5.04 years after tax and 5.55 years before tax.

6.Contact: Zhang Xinhua

7.Tel: 13019123357

 

8  Construction project of LED industrial base

1.Total investment in the project: 1.5 billion yuan (financing 1 billion yuan)

2.Location of the construction site: Northeast Core Area of Changchun National High-Tech Industrial Development Zone

3.Method of cooperation: investment, joint venture, contractual cooperation

4.Construction contents and scale: Planned project will cover an area of700,000 m2, mainly to construct factory buildings, office buildings, warehouses and other production ancillary facilities.

5.Anticipated economic benefits: After the completion of the project and reaching its designed capacity, it will realize output value of 3 billion yuan, profit of 0.3~0.5 billion, tax payment of 30~50 million yuan and investment recovery period of 7~8 years.

6.Contact: Wu Qingjun

7.Tel: 0086-431-87019013, 13944190222

 

9  Construction project of a digital electronics industrial base

1.Total investment in the project: 10 billion

2.Location of the construction site: New Area in the west part of Changchun Jingyue Economic Development Zone

3.Method of cooperation: wholly foreign-owned, joint venture

4.Construction contents and scale: The project covers an area of100,000 m2, and the overall design will be carried out by the world top design company whose accomplishment will be innovated and unique, and will be of functionality and artistic quality. The project is composed of 4 major sections, namely production section, R&D section, incubation section, and creativity section. To introduce several world leading photoelectron products production line and to construct distributing stores of digital products, digital animation creativity park and industrial park.

5.Anticipated benefits: annual sales income of 2 billion yuan, total profit of 700 million yuan, and investment recovery period of 4 years.

6.Contact: Ding Xiaohong, Xiao Di

7.Tel: 0086-431-84532421

 

10  Industrialization project of encryption software

1.Total investment in the project: 0.6-60 billion yuan

2.Location of the construction site: Changchun National High-Tech Industrial Development Zone

3.Method of cooperation: joint venture, contractual cooperation.

4.Construction contents and scale: The project covers a floor area of4,000,000 m2for the purpose of setting up production line for peripheral production development and hardware. Construction of factory buildings, office buildings and purchase of relevant equipment.

5.Anticipated economic benefits: World industrial analysis company indicated that the global market for information safety product has reached 500 billion in 2008. According to the report from RNCOS, the comprehensive annual growth of the global market of IT safety product has increased at 15.5% from 2008 to 2012. To estimate conservatively, the project will, after the third year being fully funded, realize annual sales income of 151.266 billion yuan, annual gross profit of 128.8 billion yuan, annual tax revenue of 29.2 billion, and annual net profit of 99.6 billion which are counted at 17% of the global market (889.8 billion yuan) of information safety product.

6.Contact: Zhang Zhi

7.Tel: 0086-15164397391

 

11  Restructuring project of North Caijing Group

1. Total investment in the project: 1 billion

2. Location of the construction site: Changchun Economic and Technological Development Zone

3. Method of cooperation: Funded both by enterprises in the zone and North Caijing Group through negotiation. Both parties can restructure by means of merging or joint venture.

4. Construction contents and scale: The electron production and industrial park covers an area of100,000 m2. LC display, electronic equipment and other relevant products.

5. Anticipated economic benefits: The project will realize output value of 2 billion yuan, tax payment of 0.2 billion yuan.

6. Contact: Tian Jiming

7. Tel: 0086-431-89960821

 

12  Project with annual production of 150,000 pieces of lysine oral medicinal granules

1.Total investment in the project: 350 million

2.Location of the construction site: Bio-industryParkofChangchun Economicand Technological Development Zone

3.Method of cooperation: wholly foreign-owned, joint venture, contractual cooperation.

4.Construction contents and scale: annual production capacity of 150,000 pieces of lysine oral medicinal granules.

5.Anticipated economic benefits: annual sales income of 500 million yuan; annual profit of 150 million yuan; investment recovery period of 3 years.

6.Contact: Xu Yu, An Ran

7.Tel: 0086-431-84809808

 

13  Project with annual production of 20,000 tons of medicinal glucose powder

1.Total investment in the project: 60 million yuan

2.Location of the construction site: Changchun Wukeshu Economic Development Zone

3.Method of cooperation: joint venture, contractual cooperation, wholly foreign-owned

4.Construction contents and scale: annual production of 20,000 tons of medicinal glucose powder.

5.Anticipated economic benefits: After reaching the designed capacity, it will realize annual sales income of 120 million yuan, profit of 36 million yuan, and tax payment of 15 million yuan.

6.Contact: Zhang Xinchun

7.Tel: 0086-431-83810004

 

14  Project with annual production of 2000 tons of pharmaceutical protein

1.Total investment in the project: 300 million yuan

2.Location of the construction site: Changchun Wukeshu Economic Development Zone

3.Method of cooperation: wholly foreign-owned, joint venture

4.Construction contents and scale: annual production of 2000 tons of pharmaceutical protein.

5.Anticipated economic benefits: After reaching the designed capacity, it will realize annual sales income of 165 million yuan and profit of 99 million yuan.

6.Contact: Zhang Xinchun

7.Tel: 0086-431-83810004

 

15  Project with annual production of 5000 tons of biological product

1.Total investment in the project: 800 million yuan

2.Location of the construction site: Changchun Lvyuan Xixin Industrial Cluster

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: the project covers a total area of300,000 m2, floor area of200,000 m2.

5.Anticipated economic benefits: After the completion of the project, it will realize annual production value of 500 million yuan, annual profit of 50 million, tax payment of 10 million and investment recovery period of 7 years.

6.Contact: Xie Hong

7.Tel: 0086-431-87806877

 

16  Construction project of Changchun BCHT vaccine production base

1.Total investment in the project: 810 million yuan

2.Location of the construction site: Changchun National High-Tech Industrial Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project covers an area of125,000 m2. According to the product listing plan of the company, it will construct step by step in the new factory area live vaccine producing building, inactivated vaccine producing building, bacterial vaccine producing building, quality control office building, animal house and staff apartment, and develop progressively varicella vaccine, new inactivated hepatitis A vaccine, pertussis vaccine, rotavirus vaccine, new rabies vaccine, HIB vaccine, influenza vaccine, MMR vaccine, genetic engineering vaccine and so on.

5.Anticipated economic benefits: The project is estimated to realize: major business income of 277.83 million yuan, net profit of 53.93 million yuan in 2012; major business income of 352.83 million yuan, net profit of 89.9 million yuan in 2013; major business income of 427.83 million yuan, net profit of 122.35 million yuan in 2014; major business income of 490.33 million yuan, net profit of 148.47 million yuan in 2015; major business income of 631.84 million yuan, net profit of 198.53 million yuan in 2016; major business income of 754.47 million yuan, net profit of 251.54 million yuan in 2017; major business income of 950.21 million yuan, net profit of 322.25 million yuan in 2018.

6.Contact: Han Zhipeng

7.Tel: 0086-431-87019034, 13104431333

 

17  Construction project of no-variation genetic technology

1.Total investment in the project: 148 million yuan (financing 133.3 million yuan)

2.Location of the construction site: Northeast Core Area of Changchun National High-Tech Industrial Development Zone (east ofYisan Street, southof Taipinggou)

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: The project covers an area of80,000 m2, with floor area of54,000 m2, and plans to construct science research office building, Anpu greenhouse, seed storage room, seed cold storage room, seed warehouse and so on.

5.Anticipated economic benefits: After the completion of the project, it will realize annual sales income of 672.5 million yuan, average annual profit of 82.424 million yuan under the condition of full performance, investment profit interest margin of 52.2%, and investment recovery period of 5.12 years (including two years of construction).

6.Contact: Huang Qingkai

7.Tel: 0086-431-85542528 15843071967

 

18  Construction project of production of cephalo, penicillin, Feining granule, and flunarizine hydrochloride

1.Total investment in the project: 182.78 million yuan

2.Location of the construction site: Changchun Jiutai Economic Development Zone

3.Method of cooperation: stock cooperation

4.Construction contents and scale: Office buildings, factory building No. 1, factory building No. 2, science research and development building, comprehensive preparation factory building, Pre-treatment extraction factory building, cephalo factory building, penicillin factory building, sewage disposal plant, warehouse and so on, with gross floor area of57,000 m2.

5.Anticipated economic benefits: Annual sales income of 152.7 million yuan, average annual profit of 52.4374 million yuan, total profit of 66.3557 million yuan, pre-tax investment recovery period of 5.12 years (including construction period)

6.Contact: Hang Zhizhong

7.Tel: 15604459757

 

 

VII. Other Industrial Projects (9)

         

1  Project with annual production of 10,000 tons of plastic composite pipe

1.Total investment in the project: 40.95 million yuan.

2.Location of the construction site: Changchun Chaoyang Economic Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: annual production of 10,000 tons of plastic composite pipe

5.Anticipated economic benefits: After the completion of the project, it will realize sales income of 74 million yuan, profit of 9.3 million yuan.

6.Contact: Zhang Bo, Zhai Yunfei, Ding Lin

7.Tel: 0086-431-85109189, 85109113

 

2  Project with annual production of 2 million m3 shale porcelain granule product

1.Total investment in the project: 501.418 million yuan.

2.Location of the construction site: Dehui,Changchuncity

3.Method of cooperation: wholly foreign-owned

4.Construction contents and scale: Annual production of 2 million m3 shale porcelain granule product. The project covers an area of500,000 m2to construct production facilities such as inflating and blocking factory building, mineral pre-treatment factory building, blocking and drying factory building, basic material storehouse and so on, and construct public facilities such as boiler room, electrical substation and waters supply pumping station, and relevant ancillary facilities such as reservoir, and fire-water pond etc.

5.Anticipated economic benefits: average annual sales income of 492.544 million yuan, net profit of 65.4943 million yuan, and investment recovery period of 5.34 years (including construction period)

6.Contact: Zhang Zhenbo, Wang Hongtao

7.Tel: 0086-431-87223510, 81183399

 

3  Project with annual production of 200 sets of (Kunbo brand) environmental-friendly animal manure fermentation machine

1.Total investment in the project: 500 million yuan

2.Location of the construction site: Changde Cooperation Zone of Changchun National High-Tech Industrial Development Zone

3.Method of cooperation: joint venture

4.Construction contents and scale: annual production of 200 sets of (Kunbo brand) fermentation machine.

5.Anticipated economic benefits: After the completion of the project, it will realize annual production value of 560 million yuan, tax revenue of 28 million yuan. The project will be carried out through three phrases, after which, it will reach the goal of annual production of 1000 sets of Kunbo brand fermentation machine, annual production value of 28 million yuan, and tax revenue of 140 million yuan.

6.Contact: Wang Haibo

7.Tel: 0086-431-85542491, 13086882676

 

4  Project with annual production of 2,500 sets of engineering machinery

1.Total investment in the project: 586 million yuan

2.Location of the construction site: Special Purpose Vehicle Industrial Park of Changchun Economic and Technological Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: Construction project with annual production and assembly capacity of 25 million sets of engineering machine. The project covers an area of150,000 m2, floor area of120,000 m2, and mainly constructs factory buildings and office buildings.

5.Anticipated economic benefits: After the completion of the project, it will realize annual sales income of 1.293 billion yuan, profit of 260 million yuan, annual tax revenue of 76 million yuan, and investment recovery period of 5.65 year.

6.Contact: Zhou Yiwen

7.Tel: 0086-431-84809076, 13604361994, 13353102767

 

5  Project with annual production of 50,000 sets of wind power generation equipment

1.Total investment in the project: 85 million yuan

2.Location of the construction site: North Sector of Changchun Jiutai Economic Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: Construction of facilities with annual production of 50,000 sets of wind power generation equipment. Total land occupation of project is30,000 m2, with floor area of22,000 m2. Construction of factory buildings, office buildings as requested by the producing technique.

5.Anticipated economic benefits: After the completion of project, it will realize annual sales income of 160 million yuan, and annual profit of 40 million yuan.

6.Contact: Zhao Xiaocen

7.Tel: 0086-431—82563332

 

6  Project with annual production of 100,000 meters of FRP pipe product

1.Total investment in the project: 130 million yuan

2.Location of the construction site: North Industrial Sector of Changchun Jiutai Economic Development Zone

3.Method of cooperation: joint venture, contractual cooperation.

4.Construction contents and scale: Construction of production capacity with 100,000 linear meters of FRP pipe for water supply and drainage, total land occupation of60,000 m2, with total floor area of48,000 m2. As requested by producing technique, construction of office buildings, factory buildings and so on.

5.Anticipated economic benefits: annual sales income of 140 million yuan, annual profit of 40 million yuan, and annual tax revenue of 5.5 million yuan.

6.Contact: Qin Junfeng

7.Tel: 0086-431—82563332

 

7  Comprehensive processing project with annual production of 20,000 sets of agricultural machinery

1.Total investment in the project: 160 million yuan

2.Location of the construction site: Yushu Huancheng Industrial Cluster, inJilinProvince

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: annual production of 20,000 units/sets of agricultural machinery in all kinds.

5.Anticipated economic benefits: After the completion of project, it will realize annual sales income of 210 million yuan profit of 50 million yuan and tax revenue of 19.8 million.

6.Contact: Zhang Guoxin

7.Tel: 0086-431-83863000

 

8  Project with annual production of 6,000 complete sets of equipment of hollow load-bearing blocks production line and blocks molds

1.Total investment in the project: 69.37 million yuan

2.Location of the construction site: Yushu Huancheng Industrial Cluster, inJilinprovince

3.Method of cooperation: wholly foreign-owned, joint venture

4.Content and scale of cooperation: annual production of 6000 complete sets of equipment of hollow load-bearing block production line and blocking mold

5.Anticipated economic benefits: After the completion of project, it will realize annual sales income of 260 million yuan, profit of 33.17 million yuan and tax revenue of 10 million yuan.

6.Contact: Zhang Guoxin

7.Tel: 0086-431-83863000

 

9  Construction project of production line with annual production of 50,000 tons of carbon dioxide-based plastic

1. Total investment in the project: 280 million yuan

2. Location of the construction site: Wangjinta country, Nongan county,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: construction of production line with annual production of 50,000 tons of carbon dioxide-based plastic

5. Anticipated economic benefits: After the completion of the project, it will realize annual sales income of 940 million yuan, profit of 261.44 million yuan, tax revenue of 2.56 million yuan and investment recovery period of 2 years.

6. Contact: Wang Deyou

7. Tel: 0086-431-83220871

 

 

VIII.Industrial   ParkProjects (13)

 

1  Project of Photoelectron Import and Export Base in the Comprehensive Bonded Area

1. Total investment amount for the project: 500 million yuan

2. Construction site:ChangchunXinglong Comprehensive Bonded Area

3. Way of cooperation: The entering enterprises will make investment, and Economic and Technical Development Zone will provide overall service, enterprises joining in the bonded area can enjoy all the preferential policies endowed to the area, and all the preferential policies provided by the province, city and development zone.

4. Construction project and its scale: We will build photoelectron processing base for xport with planning building area of100,000 square metersrelying on the comprehensive bonded area.

5. Expected economic benefit: This project can realize annual production value of 1 billion yuan, tax-profit amount of 200 million yuan after it goes into operation. Period for recovery of investment (after-tax) will be 3.5 years; internal rate of return (after-tax) will be 27%.

6. Contact: Zhang Xinhua

7. Telephone: 13019123357

 

2  Project of Wooden Products Export and Import Base in the Comprehensive Bonded Area

Total investment amount for the project: 500 million Yuan

2. Construction site:ChangchunXinglong Comprehensive Bonded Area

3. Way of cooperation: The entering enterprises will make investment, and Economic and Technical Development Zone will provide overall service, enterprises joining in the bonded area can enjoy all the preferential policies endowed to the area, and all the preferential policies provided by the province, city and development zone.

4. Construction project and its scale: We will build wooden products processing base for export with planning building area of100,000 square meterrelying on the comprehensive bonded area.

5. Expected economic benefit: This project can realize annual production value of 1 billion yuan, tax-profit amount of 180 million yuan after it goes into operation. Period for recovery of investment (after-tax) will be 4 years; internal rate of return (after-tax) will be 20%.

6. Contact: Zhang Xinhua

7. Telephone: 13019123357

 

3  Project of Automotive Electronics Export and Import Base in the Comprehensive Bonded Area

1.Total investment amount for the project: one billion Yuan

2. Construction site:ChangchunXinglong Comprehensive Bonded Area

3. Way of cooperation: The entering enterprises will make investment, and Economic and Technical Development Zone will provide overall service, enterprises joining in the bonded area can enjoy all the preferential policies endowed to the area, and all the preferential policies provided by the province, city and development zone.

4. Construction project and its scale: Relying on the comprehensive bonded area, we will give full play to the industrial advantages ofChangchunas the biggest automobile production and R&D bases and to the market advantages that can radiate the whole northeast area. We will cooperate to the capacity expansion project for “1 million motors”, “1 million transmissions” and “parts and components with output value of 100 billion yuan” and establish automotive electronics import and export base.

5. Expected economic benefit: The annual production value will be three billion yuan, the profit-tax amount will be 500 million yuan, period for recovery of investment (after-tax) will be 6.5 years, and internal rate of return (after-tax) will be 18%

6. Contact: Zhang Xinhua

7. Telephone: 13019123357

 

4  Project of Ginseng Processing Base for Export in the Comprehensive Bonded Area

1.Total investment amount for the project: 400 million Yuan

2.Construction site:ChangchunXinglong Comprehensive Bonded Area

3.Way of cooperation: Investment enterprise makes investment voluntarily; Changchun Economic and Technical Development Zone may provide land transferring and plant leasing as well as preferential policy and quality service

4.Construction project and its scale: Relying on the comprehensive bonded area, ginseng processing base for export will be built, and ginseng oral liquid production line, hairdressing and skin care products production lines and 10 sets of other deep processing production facilities will be added.

5.Expected economic benefit: It is expected that the average annual sales proceeds will be one billion Yuan, the average annual profit will be 130 million Yuan, the average annual profit-tax amount will be 200 million Yuan, period for recovery of project investment will be 5.4 years (pre-tax, including construction period 2 years)

6.Contact: An Ran

7.Telephone: 86-0431-89960132

 

5  Construction project of building material logistics park

1. Total investment in the project: 900 million yuan

2. Location of the construction site: modern logistics center (at WeixingvillageofYingjuntown) of Erdao district,Changchuncity

3. Method of cooperation: wholly foreign-owned, contractual cooperation

4. Construction contents and scale: The project covers an area of300,000 m2, and plans to construct210,000 m2of building material processing center and building material logistics center for the purpose of building up standard production factory, storage house, and production and management house to realize the concentration effect of building material logistics industry, developing into information, automation, network, and intelligent centered logistics enterprises, and to drive the development of the service industry of Erdao district.

5. Anticipated economic benefits: After the completion of the project, it will greatly improve the economic development of Erdao district, boost the employment, and upgrade the overall pattern of building material market.

6. Contact: Liu Xingyan

7. Tel: 0086-431- 84646772

 

6  Construction project of medicine logistics park

1.Total investment in the project: 900 million yuan

2.Location of the construction site: modern logistics center (at WeixingvillageofYingjuntown) of Erdao distric,Changchuncity

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: The project covers an area of300,000 m2and plans to construct management center of medicine logistics park, storage house and ancillary house. Purchases of ventilator, testing and measuring equipment. Installation of information system, inspection system, automobile weighing, conveyor, delivery vehicle, high three-dimensional shelf, stacker, fork truck, sag filling machine, sag closer and other ancillary equipment so as to realize the concentration effect of medicine logistics enterprise.

5.Anticipated economic benefits: After the completion of the project, it will become the biggest medicine logistics base in Northeast China affectingJilinprovince and the entire northeast region.

6.Contact: Liu Xingyan

7.Tel: 0086-431- 84646772

 

7  Construction project of international food industrial park

1. Total investment in the project: 10 billion yuan

2. Location of the construction site: Northeast Core Area of Changchun National High-Tech Industrial Development Zone

3. Method of cooperation: investment, financing, contractual cooperation

4. Construction contents and scale:

The project will cover an area of 3 square km, 1 square km of which will be started in the first phase. According to the plan, lay foundation in three years, receiving effect in five years, and making significant progress in ten years. By 2020, it is estimated that the enterprises in the zone will reach the number of 1000.

5. Anticipated economic benefits:

After the completion of the construction, the total production value is anticipated to be 7 billion yuan, profit 1.5 billion yuan, and tax payment 0.3 billion yuan.

6. Contact: Zhang Fusheng

7. Tel: 0086-431-85542551, 15843071966

 

8  Construction project of financial industrial   park of Northeast Asia

1.Total investment in the project: 7 billion yuan.

2.Location of the construction site: New Area in the west part of Changchun Jingyue Economic Development Zone

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: The project covers an area of100,000 m2with four major function sections, namely international Fengtou fund industrial park, PE capital park, emerging industry incubation base, financial service center. After the completion of the project, it will raise fund around the world and form a service industry including emerging project incubation, financial service, quality project road show, mature project financing, and project listing.

5.Anticipated economic benefits: annual sales income of 3 billion yuan, total profit of 1 billion yuan and investment recovery period of 5 years.

6.Contact: Ding Xiaohong, Xiao Di

7.Tel: 0086-431-84532421

 

9  Construction project of sika deer industrial park

1.Total investment in the project: 516 million yuan\

2.Location of the construction site: medicine industrial park of Shuangyang Economic Development Zone of Changchun city

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: sika deer product deep processing project, Lubao energy drinking project, Lubao health preserving liquor project, skin caring cosmetics product project, packaged product processing project, project of development and research center for sika deer product, project of quality inspection center for sika deer product, project of breeding center of quality sika deer, processing project of specialized fodder, project of demonstrative farm of specialized fodder, project of trading platform of sika deer product.

5.Anticipated economic benefits: After the commencement of the production, it will realize production value of 1.1327 billion yuan.

6.Contact: Zhang Dong

7.Tel: 0086-431-84152268

 

10  Construction project of Euro-American industrial park

1. Total investment in the project: 5 billion yuan

2. Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: joint venture, contractual cooperation

4. Construction contents and scale: the planned project occupies an area of 2 square km and will be constructed by stages in batches. The first phase plans to cover an area of200,000 m2with150,000 m2for factory buildings,10,000 m2for affiliate buildings. The project covers a total area of2,194,000 m2, with total floor area of3,200,000 m2to construct office buildings and factory buildings as requested be the producing techniques.

5. Anticipated economic benefits: Construction period takes up 5 years and will be tumbling-type development. Investment recovery period is 8.5 years. Accounted at 85% of the occupancy rate of the factory buildings, it is estimated to realize annual production value of 3 billion yuan and tax payment of 0.2 billion yuan according to the number of industrial clusters introduced into the park.

6. Contact: Yan Qingguo

7. Tel: 0086-431-81501716

 

11  Construction project of mould industrial park

1.Total investment in the project: 700 million yuan

2.Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: construction of 8 standardized mould factory buildings which cover an area of about7,000 m2, construction of relevant civil engineering and public facilities in accordance with modern small/medium size mould production line.

5.Anticipated economic benefits: annual sales income of 0.8 billion yuan, profit of 160 million yuan and annual tax revenue of 76 million yuan.

6.Contact: Yan Qingguo

7.Tel: 0086-431-81501716

 

12  Construction project of automotive electronics producing base

1.Total investment in the project: 900 million

2.Location of the construction site: Changchun Xixin Economic and Technological Development Zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: the project will cover an area of more than150,000 m2and construct office building, factory building and so on as requested by the producing technique.

5.Anticipated economic benefits: after the completion of the project and the commencement of production, it is expected to realize annual production value of 3.5 billion yuan, profit of 590 million yuan, and annual tax revenue of 160 million and investment recovery period of 3.2 years.

6.Contact: Yan Qingguo

7.Tel: 0086-431-81501716

 

13  Construction project of electric motorcycle industrial base

1.Total investment in the project: 740 million yuan

2.Location of the construction site: Changchun Xixin economic & technological development zone

3.Method of cooperation: joint venture, contractual cooperation

4.Construction contents and scale: annual production of 130,000 motorcycles.

5.Anticipated economic benefits: because of the policies of the country toward the subsidy and tax of motorcycle is uncertain, profit and tax revenue estimation can not be achieved. The sales income is anticipated to be 12.35 billion yuan.

6.Contact: Yan Qingguo

7.Tel: 0086-431-81501716

 

 

IX Urban Construction Projects (10)

 

1  Project of primary land development of the cluster in Yongchun town, Changchun city

1. Total investment in the project: 62.4 billion yuan (including 50 billion yuan for land arrangement, 12.4 billion yuan for construction)

2. Location of the construction site: the area around Yongchun town, Nanguan district,Changchuncity. To be specific, withYitongRiveras the east border,Changchunadministrative boundary as the south and west border, and the belt highway as the north border

3. Method of cooperation: land revenue buy-back, fixed proportion recovery in accordance with actual amount of investment.

4. Construction contents and scale: The construction project mainly includes land arrangement and construction.

Land arrangement

The first one is collective land expropriation. According to relevant state laws and regulations and local government regulatory documents, conduct expropriation on the collective land in this project (including expropriation of collective land and buildings (structures) on the land).

The second one is compensation for expropriation of houses on state-owned land. According to the request of urban planning and city operations, conduct land arrangement of receded and purchased state-owned land which needs to be removed (including expropriation of collective land and buildings (structures) on the land)

Construction

The Main part of the project is construction of the road network of Yongchun cluster with “Five Vertical and Three Horizontal” trunk roads (for details, see the road network of Yongchun Cluster), to establish macro regional environment of Yongchun district and improve the capability of attracting investments. The “Five Vertical” stands for extension line of Yatai Street, extension line of Renmin Street, extension line of Qianjin Street, extension line of Fangcao Street, and extension line of Chaoyue Street; the “Three Horizontal” stands for Yongchun No. 3 Street, Yongchun No. 5 Street, and Yongchun No. 8 Street. The total length is76 mileswith 3.1 billion yuan of planned investment. Auxiliary projects such as water supply and power supply will also be partly completed.

5. Anticipated economic benefits: recovery of capital of 131.45 billion yuan and profit of 65.72 billion yuan in five years.

6. Contact: Wang Hao

7. Tel: 0086-0431-88014993

 

2  Project of introduction of Songhua rive to Yushu city

1. Total investment in the project: 287.1 million yuan

2. Location of the construction site: Yushu,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation, BOT

4. Construction contents and scale: annual introduction volume of 36.85 million m3 water fromSonghuaRiver

5. Anticipated economic benefits: After achievement of designed capacity, the project will realize sales income of 66.33 million yuan, profit of 8.83 million yuan, and tax payment of 4.37 million yuan.

6. Contact: Zhang Yaojun

7. Tel: 0086-431-83627748

 

3  Restructuring project of Fufeng area (Dongfang Chuangyi City)

1.Total investment in the project: 2.8 billion yuan

2.Location of the construction site: Fufeng area, Chaoyang district,Changchuncity

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: Fufeng area (1.7 square km) has been listed as the key shantytown restructuring project byChangchuncity. It enjoys the preferential policy for shantytown and the basic research and estimation have been accomplished.

5.Anticipated economic benefits: To estimate at current price, the project will realize sales income of 3.24 billion yuan, profit of 440 million yuan and interest margin of 15.7%.

6.Contact: Zhang Bo, Zhai Yunfei, Ding lin

7.Tel: 0086-431-85109189 85109113

 

4  Restructuring project of Binhe neighborhood

1.Total investment in the project: 6 billion yuan

2.Location of the construction site: adjacent toJilinroad and the east bank ofYitongRiver, in Erdao district of Changchun city

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: the project covers land area of298,000 m2and is adjacent toJilinroad and the east bank ofYitongRiver. Situated in the golden belt ofChangchuncity, it is advantageous to build up a multifunctional, highly efficient, large commercial complex which will consist of upscale hotel, office building, large scale integrated shopping center, upscale residential community, and recreation and leisure spot.

5.Anticipated economic benefits: The construction site is surrounded by companies and populous residential community, with strong consuming demands to support commercial operations. Viewing from the current commercial development, here is the fifth commercial ring whichChangchuncity pays close focus to construct. The scale and status of the shopping and catering industry have begun to take shape. With large commercial demanding and promising development status, the commercial prospect is broad.

6.Contact: Liu Xingyan

7.Tel: 0086-431- 84646772

 

5  Development project of the original land of Changchun tractor factory

1.Total investment in the project: 2 billion yuan

2.Location of the construction site: Rongguang block (to the east of Minfeng Street, to the west of Lequn Street, to the south of Dongxin Road, to the north of Rongguang Road), in Erdao district, Changchun city

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: the project covers land area of230,000 m2with construction of medium-to-high end residential community and commercial building complex with vivid features.

5.Anticipated economic benefits: The construction site is surrounded by companies and populous residential community, with strong consuming demands to support commercial operations. Viewing from the current commercial development, here is the fifth commercial ring whichChangchuncity pays close focus to construct. The scale and status of the shopping and catering industry have begun to take shape. With large commercial demanding and promising development status, the commercial prospect is amazingly broad.

6.Contact: Liu Xingyan

7.Tel: 0086-431- 84646772

 

6  Comprehensive development project of the plot between Dajing Road and Chongqing Road

1.Total investment in the project: 1 billion yuan

2.Location of the construction site: from Dajing Road in the east, to Nonghang Alley in the west, and from Baixin Shoe Company on Chongqing Road in the south, to Bei’an Road in the north, in Changchun city

3.Method of cooperation: overall remising, to be developed by wholly foreign-owned company

4.Construction contents and scale: This plot is marked out as Grade 1 commercial land and Grade 1 residential land with land area of37,000 m2. There are currently 239 households and 8 industrial companies. Planning conditions include plot ratio no more than 4, building height limitation no more than50 meters, floor area of148,000 m2, greening rating no less than 25% and building density no more than 30%.

5.Anticipated economic benefits: This plot is situated in the center ofChangchuncity and core area of the commercial golden street –Chongqing Road. To its north side, the most upscale urban complex inChangchunis being planned and constructed, so that the plot has great appreciation potential and is suitable for developing and constructing upscale commercial area, five star hotel, commercial office building and commercial apartment.

6.Contact: Zhang Xisheng, Yan Minghua

7.Tel: 0086-431-85284272, 85289169

 

7  Comprehensive restructuring and development project of shantytown area near Hongda Trade Center

1.Total investment in the project: 500 million yuan

2.Location of the construction site: from Fulai Alley in the east, to Minkang Road in the west, and from Xisandao Road in the south, to Hongda Trade Center on Xisidao Road in the north, in Changchun city

3.Method of cooperation: overall remising, to be developed by wholly foreign-owned company

4.Construction contents and scale: This plot covers land area of18,400 m2with over 300 households and is suitable for constructing upscale commercial office building, medium scale residential building and larger/medium size service industry project.

5.Anticipated economic benefits: Traffic system in this area is highly developed, ensuring great convenience for travelling. The plot is surrounded by Science and Technology Commission of Jilin Province, Jilin Provincial Department of Science and Technology, Bureau of Transportation of Changchun city, and other provincial or municipal organs as well as multiple upscale residential communities, large scale commercial, catering and service plots. There are strong consuming demands and rapid rise in value of real estates. It is suitable to construct high end commercial office building, medium-to-high end residential apartment, and large/medium size service business project in this area.

6.Contact: Zhang Xisheng, Yan Minghua

7.Tel: 0086-431-85284272, 85289169

 

8  Restructuring second phrase project of dilapidated building of Yongchun residential area

1. Total investment in the project: 300 million yuan

2. Location of the construction site: fromYongchun   Roadin the east, toZhongyuanMansionin the west, and fromChangchun Streetin the south, toXisan Roadin the north, inChangchuncity

3. Method of cooperation: overall remising, to be developed by wholly foreign-owned company

4. Construction contents and scale: This plot covers land area of7,500 m2, and is owned by Changchun Wanhe Property Management Company. The plot was a surplus plot in the first phase of dilapidated buildings renovation project in Yongchun, and for various reasons, it was left unused for nearly ten years in the second phase. There are 160 households and 3 enterprises with demolition area of8,000 m2and3,600 m2respectively.

5. Anticipated economic benefits: The plot is located in the Damalu Yongchun Commercial Ring nearChangchun Street, neighboring the increasingly prosperousYongchunTradeCenterand uniquely featuredChangchunLightingWholesaleCenterto the north. Multiply schools and hospitals in the surrounding area bring strong cultural atmosphere and specialized characteristics. With upscale residential community, large-size commercial and catering service spots, this plot has strong consumption demands and rapid rise in value of real estates, suitable for developing and constructing business office building, modern commercial service or upscale residential community.

6. Contact: Zhang Xisheng, Yan Minghua

7. Tel: 0086-431-85284272, 85289169

 

9  Real estate development project of a living island outside the beltway

1. Total investment in the project: 6.1 billion yuan

2. Location of the construction site: from A-2 Road in the east, to Qiancheng Road in the west, and from Dongfeng Road in the north, to Tengfei Road in the south, in Changchun Xixin Economic and Technological Development Zone

3. Method of cooperation: underwrite land leveling costs in the early stage, and obtain land use rights through bidding, auction, or listing

4. Construction contents and scale: land to be used100 hectares(planned plot ratio 1.5~2.0)

5. Anticipated economic benefits: profit of about 700 million yuan

6. Contact: Liu Xiangdong

7. Tel: 0086-431-81501613

 

10  Construction and development project of the plot near Changchun No.52 Middle School and the weighing apparatus factories

1.Total investment in the project: 120 million yuan

2.Location of the construction site: to the east ofJilin   Street, westof the front gate ofWuyiGarden, south of the southern walls ofWuyiGarden, and north ofJilinroad, inJilinblock, Erdao district,Changchuncity

3.Method of cooperation: wholly foreign-owned, contractual cooperation

4.Construction contents and scale: The project covers land area of20,000 m2and plans to construct high grade office building and commercial complex building.

5.Anticipated economic benefits: This plot is adjacent toJilin Roadwhich leads to theLongjiaInternationalAirportand will become a window of the city to display its styles and features and communicate with the world. Under the strong supported of the government, the entireJilinroad is taking on a brand new look with the emergence of many real estate projects. The acceleration of urban renewal speeds up the development of real estate, and the development of the real estate industry also spurs the economic development of this region – each supplementing and benefitting the other. Building up a commercial center here will bring considerable economic effects.

6.Contact: Liu Xingyan

7.Tel: 0086-431- 8464677

 

11  Project of integration of combined heat and power generation and urban central heating in Yushu

1. Total investment in the project: 30 million yuan

2. Location of the construction site: northern suburb of Yushu,Changchuncity

3. Method of cooperation: joint venture, contractual cooperation, BOT

4. Construction contents and scale: installed capability of 24MW.

5. Anticipated economic benefits: After reaching the designed capacity, the project will realize annual sales income of 600 million yuan, profit of 52 million, and tax payment of 36 million yuan.

6. Contact: Song Xingwang

7. Tel: 0086-431-833622795